3rd Quarter 2009 Volume 01 - No. 5
PJIAE PROJECTS KEEP AIM ON TRAVELER COMFORT AND ISLAND DEVELOPMENT
With the completion of one major infrastructural project in sight, PJIAE is soon to turn its attention to another project aimed at easing the flow of passengers; albeit that the project nearing completion is roadside, while the other in start-blocks is airside. The project on the roadside called on motorists driving through the airport area to take note of another detour, as the upgrade of the road network is reaching completion. As of Wednesday October 7, 2009, and until further notice, the new roundabout has been open for traffic coming from both the Maho and Simpson Bay directions.

“We started the second half of the roundabout; so that - although it is not fully covered with asphalt - part of it is in use while work continues on the eastern half,” said PJIAE Technical Director Mr. Mirto Breell. He expected the final layer of asphalt to be laid by the third week of October, after which the road works should finalize by week 45, the second week in November. “After that we will turn our full attention to the parking lot and work on completing that by February 2010. We are on target. Very much so,” he said.

The new road is almost finishedMeanwhile, while work is being finished on the road, traffic heading towards Maho will be led through the roundabout and will continue along the Simpson Bay lagoon, around the visitor’s parking lot. Traffic coming from the Maho direction will go around the parking lot, and over the roundabout to head towards Simpson Bay. Motorists leaving the frontier road at the Airport Terminal Building, will turn either left or right around the roundabout, to head in either the directions of Maho or Simpson Bay.

The airport infrastructure upgrade works started in May, with the objective of improving safety and enhancing traffic flow in the area. Drs. Eugene Holiday, President of the Princess Juliana International Airport operating company (PJIAE) repeated earlier calls for caution as the works progress. “These temporary detours are an important facet in the island’s overall development. This project will result in the reduction of traffic congestion, thus reducing the loss of valuable productive time and reducing the chances of people missing flights. At the completion of this project safety of the traveling public, as well as meters and greeters will also have been improved. So we again ask for patience of the general public, but most of all for caution of motorists,” drs. Holiday said.

The new road represents a US$2 million investment. This project forms an integral part of the adjusted Airport Masterplan and is aimed at securing and enhancing adequate traffic flow to/from the airport and airport parking; relinquishing the pedestrian crossing over the main road and increasing car parking.

The project on airside that is now in starting blocks concerns the addition of two gates at the southwestern end of the airport building. The number of B-Gates will be increased to 5, with the installation of two single sliding doors. The objective is to enhance capacity of the B-lounge during peak hours, explained Mr. Breell. He said it had been brought to PJIAE’s attention, that sometimes, when multiple aircraft are being boarded from the B-lounge, things can get cramped in that area. “With the additional doors, even when all their flights come in at the same time, the airlines that use this area will have something to fall back on, so they can board more than one aircraft at once,” Mr. Breell said.

The B-gatesThe B-Lounge is used predominantly by the lighter commuter airlines that do not dock at the jetbridges. Passengers walk to or are bussed to their waiting planes from these gates that are located on the ground floor of the terminal building. Work will start as soon as the project proposal by the contractor has been reviewed and approved.

Drs. Holiday placed the additional gates in light of PJIAE’s aim at staying in the foreground of aviation in the region. “Customer comfort is important to us. The airlines pointed out a bottleneck and we complied because we agreed that these additional doors will help to ease passenger flow,” he said.

With the additional doors, the terminal building will have 13 gates. The facility was commissioned in 2006. Spanning 30,500 square meters, it has four floors, 46 check-in counters, eight transfer desks, 10 immigration booths and five emigration booths. With a capacity to handle 2.5 million passengers annually, it took travel in the north eastern Caribbean to new heights, transferring PJIAE from an airport to more than a place where one catches a flight; the new building is fully air-conditioned, has a shopping mall, a bank, a food court and many other amenities passengers consider comfort.
Click here to download the complete Horizons newsletter

 

back to top   |  printer-friendly version

Search through this website

Check your flight info
 

Please fill out the form below to subscribe to this newsletter.

First name *

Last name

E-mail address *

Previous issues:

> Horizons Digital 1
June - Oct 2008

> Horizons Digital 2
Dec 2008 - Jan 2009

> Horizons Digital 3
1st Quarter 2009

> Horizons Digital 4
2nd Quarter 2009